Module 4 · Lesson 4.2

The six buckets in every development budget

The capital stack is where the money comes from.

The course / Module 4: Paying for it / Lesson 4.2

Last reviewed

The capital stack is where the money comes from. The development budget is where it goes. Almost every budget sorts into six buckets:

  1. Acquisition: land, plus any existing buildings.
  2. Hard costs: construction, site work and a contingency.
  3. Soft costs: architecture, engineering, legal, the market study, permits, insurance, application fees.
  4. Financing costs: construction interest and loan and bond fees.
  5. Developer fee: capped by the state.
  6. Reserves: operating, replacement and lease-up reserves the investor and lender require.
Example, made-up numbers: a $20M budget might be $1M acquisition, $14M hard costs, $1.5M soft costs, $1M financing, $2M developer fee and $0.5M reserves.

Most of buckets 2 through 5 lands in eligible basis. Land and reserves don't. See what counts in basis.

Key points
  • Acquisition, hard, soft, financing, fee, reserves.
  • Hard costs are the biggest bucket.
  • Not every bucket earns credits.